Bridge Projects

Share Bridge Projects on Facebook Share Bridge Projects on Twitter Share Bridge Projects on Linkedin Email Bridge Projects link

There are currently six bridges under construction and design within the City of Palm Springs, with a total cost estimate of $226 million. The City is also working with Coachella Valley Association of Governments (CVAG) to access funding for two bridges at low-water crossings on Indian Canyon Drive. CVAG has applied for a $50 million grant and will hear soon on whether it has been awarded the funding.

BRIDGE PROJECT STATUS UPDATES, 6-13-24

There are currently six bridges under construction and design within the City of Palm Springs, with a total cost estimate of $226 million. The City is also working with Coachella Valley Association of Governments (CVAG) to access funding for two bridges at low-water crossings on Indian Canyon Drive. CVAG has applied for a $50 million grant and will hear soon on whether it has been awarded the funding.

BRIDGE PROJECT STATUS UPDATES, 6-13-24

  • CVAG Receives $50 million to improve Indian Canyon Drive and Keep it Open

    Share CVAG Receives $50 million to improve Indian Canyon Drive and Keep it Open on Facebook Share CVAG Receives $50 million to improve Indian Canyon Drive and Keep it Open on Twitter Share CVAG Receives $50 million to improve Indian Canyon Drive and Keep it Open on Linkedin Email CVAG Receives $50 million to improve Indian Canyon Drive and Keep it Open link

    FOR IMMEDIATE RELEASE

    Thursday, December 7, 2023

    RIVERSIDE – The California Transportation Commission (CTC) today awarded $50 million for Addressing Climate Change, Emergencies, and Sandstorms (ACCESS) Project on Indian Canyon. The ACCESS project, spearheaded by the Coachella Valley Association of Governments, aims to solve the frequent road closures that have plagued the City for decades.

    The funding was unanimously approved as part of the CTC’s inaugural cycle of the Local Transportation Climate Adaptation Program (LTCAP). Indian Canyon was one of only two projects statewide that received the CTC’s highest priority ranking. The project was also highlighted during the CTC’s meeting in the City of Riverside.

    “This is a monumental moment. These prolonged and frequent closures of Indian Canyon are not just a minor headache for one city; they put roads across the western Coachella Valley at a standstill and have devastating impacts on our ability to get people to Desert Regional Medical Center at a time when every second counts,” said Desert Hot Springs Mayor Scott Matas, Chair of CVAG. “Our entire region worked collaboratively to prioritize improvements along Indian Canyon and we’re grateful the California Transportation Commission continues to financially support our efforts. I know I join residents across the Coachella Valley in saying ‘finally!””

    Today’s exciting news comes on the heels of actions taken Monday at a joint meeting of CVAG’s Executive and Transportation Committees, which authorized the CVAG Executive Director to take the necessary steps to accept the funds. CVAG’s Executive and Transportation Committees also unanimously approved amendments to the existing engineering and design contract to keep the project on schedule.

    “This much needed funding for an elevated bridge at North Indian Canyon is absolutely outstanding news,” said Palm Springs Councilmember Lisa Middleton, who serves on CVAG’s Transportation Committee and has long worked to deliver this project to the west end of the Coachella Valley. “Following the destructive impacts of the 2019 St. Valentine’s flood in Palm Springs, it became clear that a bridge at North Indian Canyon was desperately needed and we tripled our efforts, which has led to this terrific outcome. We are extremely grateful to the California Transportation Commission, CVAG, and all of the Coachella Valley cities for partnering with Palm Springs to help move this project forward. We understand the importance of Indian Canyon to thousands of Coachella Valley residents – and your relief is finally at hand.”

    The ACCESS – Indian Canyon grant application stemmed from the solutions that were first identified in the Flood and Blowsand Risk Assessment and Improvement Plan for the Western Coachella Valley. The flooding and blowsand study analyzed projects across the Cities of Desert Hot Springs, Palm Springs and Cathedral City. Indian Canyon was quickly prioritized by CVAG’s Executive and Transportation Committees as it serves as a critical arterial for both Palm Springs and Desert Hot Springs.

    “Not only is this roadway a critical artery for commuters, it’s also the main artery to the Coachella Valley’s only level one Trauma Center at Desert Regional Medical Center,” said Palm Springs Mayor Grace Garner. “This is about saving lives; especially when there is an emergency that shuts the road down for a prolonged period of time like we recently experienced with Tropical Storm Hilary. On behalf of our residents, we are deeply thankful to the California Transportation Commission for recognizing that this is a life and death issue – and for stepping up to help fund this much needed new bridge, which will improve the quality of life for everyone who depends on North Indian Canyon to get to their destination.”

    In shaping the grant application, CVAG wanted to ensure that no other project better aligned with the CTC’s vision for the LTCAP funding. The ACCESS – Indian Canyon project includes improvements that protect at-risk transportation infrastructure, increase the community’s climate resiliency, enhance mobility, preserve the environment, and improve public health and safety for residents and visitors.

    The CTC received 22 project nominations totaling over $388 million in funding requests. An evaluation team consisting of CTC and Caltrans staff reviewed project nominations based on the criteria identified in the Commission’s adopted guidelines. The award from the CTC was recommended by CTC staff in November.

    “I am thrilled CTC approved $50 million of funding for CVAG's ACCESS project, a crucial initiative to address flooding and blowsand road closures on Indian Canyon Drive,” said Assemblymember Greg Wallis. “As one of only two projects throughout the state that received the maximum grant award, this investment ensures the Coachella Valley obtains its fair share of resources to build safer, healthier, and more resilient communities in the 47th Assembly District. Together, we can build a transportation system that withstands climate challenges and secures our community's well-being, positively impacting lives and sustaining our local economy.”

    Added Assemblymember Eduardo Garcia: “We are grateful to see unprecedented state investments continue to support our community’s urgent infrastructure needs. This $50 million grant will vastly improve public safety, safeguards during storms, and roadway connectivity. We applaud CVAG and the City of Palm Springs for their leadership and commitment to work collaboratively as one, united Coachella Valley region.”

    A number of agencies, organizations and individuals have also voiced their support for CVAG’s funding applications: the Cities and Towns of Cathedral City, Coachella, Desert Hot Springs, Indio, La Quinta, Palm Desert, Palm Springs, Rancho Mirage, Twenty-Nine Palms and Yucca Valley; Agua Caliente Band of Cahuilla Indians; County of Riverside and Supervisor V. Manuel Perez; Riverside County Transportation Commission (RCTC); Palm Springs Police and Fire Departments; Palm Springs Unified School District; College of the Desert; Coachella Valley Economic Partnership; Coachella Valley Housing Coalition; Desert Care Network, including Desert Regional Medical Center and Hi-Desert Medical Center; Desert Healthcare District/ Foundation; Desert AIDS Project; American Medical Response; Coachella Valley Conservation Commission; Desert Community Energy; and UC Riverside’s Dr. Lynn Sweet.

    “Today’s vote is welcome news as we work together as a region to keep our critical arterials open,” said Coachella Mayor Steve Hernandez, Chair of CVAG Transportation Committee. “Whether it is Indian Canyon or projects like Monroe Street and Avenue 50 in the eastern Coachella Valley, we need investments like these to ensure a safe and reliable way for our communities to get to work, school and home.”

    Additional project details are here: https://cvag.org/library/pdf_files/trans/ACCESS_Fact_Sheet.pdf The project’s design and engineering are underway.

  • Indian Canyon Drive Bridge Project (CVAG)

    Share Indian Canyon Drive Bridge Project (CVAG) on Facebook Share Indian Canyon Drive Bridge Project (CVAG) on Twitter Share Indian Canyon Drive Bridge Project (CVAG) on Linkedin Email Indian Canyon Drive Bridge Project (CVAG) link
    supporting image

    Coachella Valley Association of Governments (CVAG) in July 2023 applied for Local Transportation Climate Adaptation Program (LTCAP) funding.

    New grant program administered by the California Transportation Commission (CTC)

    Addressing Climate Change, Emergencies and Sandstorms (ACCESS) Indian Canyon Drive project seeks $50 million.

    ACCESS will provide:

    • Two bridges at low-water crossings on Indian Canyon Drive.
    • Two miles of a solar shaded bike path, that connects Desert Hot Springs to CV Link.
    • A wildlife undercrossing protecting the ecosystem for endangered and protected species in alignment with the Coachella Valley Multiple Species Habitat Conservation Plan.
    • Two miles of sand fencing up to Amtrak’s Palm Springs Station
    • The total project cost is $74.9 million.
    • Considerably lower than the $250 million original estimates to build a bridge for the entire length of Indian Canyon Drive.
    • CTC to announce grant awards in December.

    City and CVAG have met with regional officials, Governor Newsom, Congressman Calvert and are hopeful a $50 million grant will finally address the decades commuter headache.

  • Indian Canyon Drive over the Union Pacific Railroad from Garnet to Train Station Road

    Share Indian Canyon Drive over the Union Pacific Railroad from Garnet to Train Station Road on Facebook Share Indian Canyon Drive over the Union Pacific Railroad from Garnet to Train Station Road on Twitter Share Indian Canyon Drive over the Union Pacific Railroad from Garnet to Train Station Road on Linkedin Email Indian Canyon Drive over the Union Pacific Railroad from Garnet to Train Station Road link

    Project Status: Under Construction - 3-year construction schedule

    Location: Indian Canyon Drive over the Union Pacific Railroad from Garnet to Train Station Road.

    Project Description: Widening of the bridge over the Union Pacific Railroad tracks will correspond with the 6-lane roadway constructed from Garnet Avenue to Interstate-10

    Project Justification: This is a missing link to allow for 6-lane roadway matching what Caltrans built for the I-10/Indian Canyon interchange.

    Estimated Cost: $45 million

  • South Palm Canyon Drive Bridge Widening at Arenas Canyon South

    Share South Palm Canyon Drive Bridge Widening at Arenas Canyon South on Facebook Share South Palm Canyon Drive Bridge Widening at Arenas Canyon South on Twitter Share South Palm Canyon Drive Bridge Widening at Arenas Canyon South on Linkedin Email South Palm Canyon Drive Bridge Widening at Arenas Canyon South link

    Estimated Construction Start Date: June 2024

    Location: South Palm Canyon Drive from Murray Canyon to Bogert Trail

    Project Description: Bridge widening includes construction of a new bridge and drainage improvements at Arenas Canyon South drainage channel.

    Project Justification: Eliminate flooded roadway with a four-lane bridge on South Palm Canyon Drive

    Estimated Cost: $9 million

    City Council Staff Report, June 13, 2024

  • Ramon Road over the Whitewater Channel

    Share Ramon Road over the Whitewater Channel on Facebook Share Ramon Road over the Whitewater Channel on Twitter Share Ramon Road over the Whitewater Channel on Linkedin Email Ramon Road over the Whitewater Channel link

    Estimated Start of Construction: Late 2024 or Early 2025

    Location: Ramon Road Bridge, 0.8 miles East of Gene Autry Trail.

    Project Description: Widen 4-lane bridge to 6-lane bridge, seismic retrofit as necessary, scour countermeasures.

    Project Justification: The existing street is six lanes on either side of the bridge. The four-lane bridge is a bottleneck. There is no pedestrian sidewalk on the north side of the bridge.

    Estimated Cost: 48 million

    Link to City Council Staff Report, June 13, 2024

  • Vista Chino Bridge over Whitewater Channel

    Share Vista Chino Bridge over Whitewater Channel on Facebook Share Vista Chino Bridge over Whitewater Channel on Twitter Share Vista Chino Bridge over Whitewater Channel on Linkedin Email Vista Chino Bridge over Whitewater Channel link

    Estimated Start of Construction: August 2026

    Notes: 65 percent of plan completed - starting right-of-way phase.

    Location: Vista Chino at Whitewater Channel Project

    Description: Replace existing 4 lane roadway with a new 4 lane bridge. High cost bridge project agreement required.

    Project Justification: Eliminate frequent road closures due to flooding and sand buildup on windy days.

    Estimated Cost: $95 million

  • South Palm Canyon Drive Over Tahquitz Creek Channel

    Share South Palm Canyon Drive Over Tahquitz Creek Channel on Facebook Share South Palm Canyon Drive Over Tahquitz Creek Channel on Twitter Share South Palm Canyon Drive Over Tahquitz Creek Channel on Linkedin Email South Palm Canyon Drive Over Tahquitz Creek Channel link

    Estimated Construction Start Date: January 2025

    Location: South Palm Canyon Drive, 0.4 miles South of Ramon Road Project

    Description: Replace four-lane bridge with a new, wider four-lane bridge.

    Project Justification: The new bridge will have proper lane widths and sidewalks for pedestrians and bicyclists

    Estimated Cost: $14 million

  • E. Palm Canyon Drive over Palm Canyon Wash

    Share E. Palm Canyon Drive over Palm Canyon Wash on Facebook Share E. Palm Canyon Drive over Palm Canyon Wash on Twitter Share E. Palm Canyon Drive over Palm Canyon Wash on Linkedin Email E. Palm Canyon Drive over Palm Canyon Wash link

    Estimated Construction Start Date: June 2025

    Location: East Palm Canyon Drive, 0.5 miles East of Farrell Drive

    Project Description: Bridge rehabilitation project, to widen four-lane bridge to add shoulders and sidewalks.

    Project Justification: No shoulders and sidewalks along the bridge. Pedestrian bridge on north side, but nothing for south side.

    Estimated Cost: $15 million

Page last updated: 13 Jun 2024, 06:45 PM