Engineering Projects
CAPITAL IMPROVEMENT PROGRAM (CIP)
The City’s 5-Year Capital Improvement Program (CIP) includes major projects to construct new, replace or upgrade existing City infrastructure including but not limited to its bridges, buildings, facilities, drainage systems, parks, streets, highways, traffic signals and utilities.
CAPITAL IMPROVEMENT PROGRAM (CIP)
The City’s 5-Year Capital Improvement Program (CIP) includes major projects to construct new, replace or upgrade existing City infrastructure including but not limited to its bridges, buildings, facilities, drainage systems, parks, streets, highways, traffic signals and utilities.
-
Playground Equipment Shade Structures - Demuth Park & Baristo Park
Share Playground Equipment Shade Structures - Demuth Park & Baristo Park on Facebook Share Playground Equipment Shade Structures - Demuth Park & Baristo Park on Twitter Share Playground Equipment Shade Structures - Demuth Park & Baristo Park on Linkedin Email Playground Equipment Shade Structures - Demuth Park & Baristo Park linkProject Description: Construct shade structures over the two playgrounds at Demuth Park and the playground at Baristo Park
Project Status: Construction (Notice to Proceed)
Project Justification: Intense summer heat, makes playground equipment hot to the touch and unusable by children for large parts of the day. Shade structures will provide some relief and allow for children to play outdoors.
Funding: Community Development Block Grant (CDBG). The CDBG program can fund projects like this when located in a low/moderate income area of the City.
-
E. Palm Canyon Bridge over Palm Canyon Wash
Share E. Palm Canyon Bridge over Palm Canyon Wash on Facebook Share E. Palm Canyon Bridge over Palm Canyon Wash on Twitter Share E. Palm Canyon Bridge over Palm Canyon Wash on Linkedin Email E. Palm Canyon Bridge over Palm Canyon Wash linkLocation: East Palm Canyon Drive, 0.5 miles East of Farrell Drive
Project Description: Bridge rehabilitation project, to widen four-lane bridge to add shoulders and sidewalks.
Project Justification: No shoulders and sidewalks along the bridge. Pedestrian bridge on north side, but nothing for south side.
Project Status: Design - In Progress
Cost: $9,323,000
Funding
- Capital Projects funding
- Measure A
-
Ramon Road Bridge over Whitewater River
Share Ramon Road Bridge over Whitewater River on Facebook Share Ramon Road Bridge over Whitewater River on Twitter Share Ramon Road Bridge over Whitewater River on Linkedin Email Ramon Road Bridge over Whitewater River linkLocation: Ramon Road Bridge, 0.8 miles East of Gene Autry Trail.
Project Description: Widen four-lane bridge to six-lane bridge, seismic retrofit as necessary, scour countermeasures.
Project Justification: The existing street is six lanes on either side of the bridge. The four-lane bridge is a bottleneck. There is no pedestrian sidewalk on the north side of the bridge.
Project Status: Design - In Progress
Cost: $44,655,000
Funding
- Federal Funds - Highway Bridge Program
- Coachella Valley Association of Governments (CVAG)
- City of Cathedral City
-
Roundabout at S. Indian Canyon Drive and S. Palm Canyon Drive
Share Roundabout at S. Indian Canyon Drive and S. Palm Canyon Drive on Facebook Share Roundabout at S. Indian Canyon Drive and S. Palm Canyon Drive on Twitter Share Roundabout at S. Indian Canyon Drive and S. Palm Canyon Drive on Linkedin Email Roundabout at S. Indian Canyon Drive and S. Palm Canyon Drive linkLocation: Intersection of S. Indian Canyon Drive, S. Palm Canyon Drive and Camino Parocela
Project Description: Construct a new roundabout at the five-legged intersection.
Project Justification: As a part of the Indian Canyon Two-Way conversion study, the City Council requested the project look at a traffic signal vs. a roundabout at this intersection. The roundabout was the preferred design alternative from a traffic safety perspective and to reduce traffic accidents.
Project Status: Design - In Progress
Cost: $2,836,174
Funding: Measure J / Capital Projects funds
-
Arnico Tract Sewer - Phase 4
Share Arnico Tract Sewer - Phase 4 on Facebook Share Arnico Tract Sewer - Phase 4 on Twitter Share Arnico Tract Sewer - Phase 4 on Linkedin Email Arnico Tract Sewer - Phase 4 linkLocation: Arnico Street between E. Via Escuela and Jason Court.
Project Description: Install sewer main and sewer laterals in Arnico Street
Project Justification: The residential neighborhood of 87 homes located south of Via Escuela between Whitewater Club Drive and Gene Autry Trail was previously identified in a moderate-to-low income census tract area making public improvements in that neighborhood eligible for funding through the City's Community Development Block Grant (CDBG) Program. Over several years, the City Council funded installation of sewer improvements in phases in this neighborhood with CDBG funds. However, after the 2010 Census, this residential area was no longer identified in an eligible income area allowing for use of CDBG funds, leaving the last phase of homes on Arnico Street without connections to the City’s sewers and relying on septic tanks.
Project Status: Construction - Notice of Completion Staff Report
Cost: $785,000
Funding: Measure J
-
Recreation Fields LED Lighting Upgrades
Share Recreation Fields LED Lighting Upgrades on Facebook Share Recreation Fields LED Lighting Upgrades on Twitter Share Recreation Fields LED Lighting Upgrades on Linkedin Email Recreation Fields LED Lighting Upgrades linkLocation: Demuth Park and Sunrise Park Ballfields
Project Description: The lights at the various park ballfields were installed in the 1950s and 1960s and utilized outdated and energy inefficient metal halide light fixtures that are no longer manufactured. This project will replace the metal halide light fixtures with energy efficient LED light fixtures and replace the wiring system.
Project Status: Construction in progress. During construction some fields at Demuth Park will not have night lighting and the City is working with sports organizations to keep programs going while this valuable improvement project is finalized.
Cost: $4,194,219
Funding: Measure J
-
South Palm Canyon Drive Bridge Widening
Share South Palm Canyon Drive Bridge Widening on Facebook Share South Palm Canyon Drive Bridge Widening on Twitter Share South Palm Canyon Drive Bridge Widening on Linkedin Email South Palm Canyon Drive Bridge Widening linkLocation: South Palm Canyon Drive from Murray Canyon to Bogert Trail
Project Description: Bridge widening includes construction of a new bridge and drainage improvements at Arenas Canyon South drainage channel.
Project Justification: Eliminate flooded roadway with a four-lane bridge on South Palm Canyon Drive
Project Status: Design - In Progress
Cost: $6,346,550
Funding: Federal funding; Coachella Valley Association of Governments (CVAG)
-
Victoria Park and Ruth Hardy Park Restroom Renovations
Share Victoria Park and Ruth Hardy Park Restroom Renovations on Facebook Share Victoria Park and Ruth Hardy Park Restroom Renovations on Twitter Share Victoria Park and Ruth Hardy Park Restroom Renovations on Linkedin Email Victoria Park and Ruth Hardy Park Restroom Renovations linkProject Description: This project will upgrade the plumbing and electrical facilities inside City owned parks. Based on Engineering and Architectural review, the project may reconstruct the restroom rather than upgrade. Alternatively, we will review the ability to construct new restrooms at these locations.
Project status: Design kick-off meeting
Cost: $950,000
Funding: Measure J
-
Traffic Signal Modifications at 14 Intersections
Share Traffic Signal Modifications at 14 Intersections on Facebook Share Traffic Signal Modifications at 14 Intersections on Twitter Share Traffic Signal Modifications at 14 Intersections on Linkedin Email Traffic Signal Modifications at 14 Intersections linkProject Description: Modify the traffic signals at14 intersections for improved visibility, add protected left-turn phasing
- N Palm Canyon/San Rafael
- N Indian Canyon/San Rafael
- N Indian Canyon/Vista Chino
- E Vista Chino/Sunrise
- E Vista Chino/Gene Autry Trail
- E Vista Chino
- Clubhouse View
- N Indian Canyon/Tachevah
- S Palm Canyon/Ramon, Ramon/Farrell
- Ramon/Vella-Kirk Douglas
- Ramon/Gene Autry Trail
- Ramon/San Luis Ray Dr.
- S Palm Canyon/Mesquite
- Dinah Shore/Gene Autry Trail
Project Status: In Progress
Cost: $4,350,500
Funding: Federal funding
-
Traffic Signal Modifications at 9 Intersections
Share Traffic Signal Modifications at 9 Intersections on Facebook Share Traffic Signal Modifications at 9 Intersections on Twitter Share Traffic Signal Modifications at 9 Intersections on Linkedin Email Traffic Signal Modifications at 9 Intersections linkProject Description: Improve traffic signals at 9 intersections with the latest in traffic safety equipment, including the installation of advanced dilemma zone detection and upgrading of ADA curb ramps.
- Tahquitz Canyon Way / Calle Encilia
- E. Palm Canyon Drive / Araby Drive
- Ramon Road / Avenida Caballeros
- Ramon Road / Compadre Road
- Farrell Drive/Via Escuela
- Sunrise Way / Tachevah Drive
- Farrell Drive / Alejo Road
- Indian Canyon Drive / 20th Avenue
- Sunrise Way / Alejo Road
Project Status: In Progress
Cost: $1,702,700
Funding: Federal Funding