Gene Autry Trail Wind Wall
Share Gene Autry Trail Wind Wall on Facebook
Share Gene Autry Trail Wind Wall on Twitter
Share Gene Autry Trail Wind Wall on Linkedin
Email Gene Autry Trail Wind Wall link
The work comprises the removals of existing wood walls, guardrails, select asphalt, and the construction of approximately 590’ long reinforced CMU brick wall, reinforced concrete-barrier stem and grade beam footing, 24” diameter CIDH Pile foundations, slurry & crack sealing, signage, and pavement markings/striping.
Schedule - Work is tentatively scheduled to start by June and continue through December 2025.
More updates will be provided, including lane closures and other pertinent information.
Concept drawing of CMU Wall, with wall heights ranging from 12 ft to 14.5 ft
Page last updated: 29 Apr 2025, 04:39 PM